Whether the test is executed in parallel or in series depends on the combination of whether the workspace's "Parallel test execution" is enabled/disabled, how the test is executed, and whether or not data features are used.
The conditions under which parallel execution and series execution are applied are as follows

Data use or not How to execute Execution when workspace Parallel test execution setting is enabled Execution when workspace Parallel test execution setting is disabled
Without data table use Execution from Run now in scenario ・Execution with other tests => Parallel ・Execution with other tests => Sequential
Execution of a test plan with parallel settings ・In one test plan => Parallel
・Multiple test plans => Parallel
・In one test plan => Sequential
・Multiple test plans => Sequential
Execution of a test plan with Sequential settings ・In one test plan => Sequential
・Multiple test plans => Parallel
・In one test plan => Sequential
・Multiple test plans => Sequential
With data table use Execution from Run now in scenario ・Using data in scenarios => Parallel
・Execution with other tests => Parallel
・Using data in scenarios => Sequential
・Execution with other tests => Sequential
Execution of a test plan with parallel settings ・Using data in scenarios=> Parallel
・In one test plan => Parallel
・Multiple test plans => Parallel
・Using data in scenarios => Sequential
・In one test plan => SeSequentialrial
・Multiple test plans => Sequential
Execution of a test plan with sequential settings ・Using data in scenarios => Sequential
・In one test plan => Sequential
・Multiple test plans => Parallel
・Using data in scenarios => Sequential
・In one test plan => Sequential
・Multiple test plans => Sequential
    • If Disable is set for Parallel test execution in the workspace, the Run in: Parallel specification in the test plan is ignored, and all tests are executed as serial runs.

Changing your password will log you out immediately. Use the new password to log back in.
First name must have atleast 2 characters. Numbers and special characters are not allowed.
Last name must have atleast 1 characters. Numbers and special characters are not allowed.
Enter a valid email
Enter a valid password
Your profile has been successfully updated.