How is the execution count calculated?
Article Summary
Share feedback
Thanks for sharing your feedback!
※ Please note that parts of this page are machine translated.
⚠︎ This is available to customers on the Startup, Small, Advanced PC, Advanced SP, and Advanced PC & SP plan.
Execution count, which can be viewed from the organization settings, is added each time the test is run. The timing of the count is when the test is completed.
For example, if a test started in January and completed in February, it will be counted as a February run.
The calculation formula is as follows:
[Scenario] × Execution environment (Edge, Chrome, etc.) × Number of [Data]
This number matches the number of [Results] (= sum of green and red numbers if looking at the results list)
Rest assured that tests that have been [Internal error] or [Canceled] are not counted in the number of executions.